Questions answered

What actually sets the price of a farm building, and free quotes from agricultural building contractors.

Get agricultural building quotes

Frequently asked

How much does an agricultural building cost?

Almost entirely on scope. A delivered frame kit, erected shell and turnkey building (groundworks, reinforced slab, doors, drainage) are three different prices for one footprint. Price the scope, not a rate per square metre: itemise groundworks, foundations, slab, frame, cladding, doors and drainage. Agricultural building contractors cost the same shed differently, so compare three quotes on one written specification.

What is the biggest hidden cost in a farm building?

Groundworks and the concrete slab. They are frequently excluded from the headline price and vary hugely with site levels and ground conditions. They are also the item most likely to generate a variation once digging starts. Ask for them as a separately priced item and ask who carries the risk on unexpected ground.

Do agricultural buildings need building regulations approval?

Planning and building regulations are separate regimes. Government guidance is clear that even where a planning application is not needed, other consents including building regulations may be required. So check with your local authority building control or a registered building control approver for your specific building. Do not assume an agricultural exemption applies.

How big can an agricultural building be under permitted development?

In England, under GPDO 2015 Part 6 Class A, a building erected, extended or altered may cover at most 1,500 m² of ground. Works or structures accommodating livestock or plant and machinery from engineering operations may cover at most 1,000 m². Height: 12m, or 3m within 3km of an aerodrome perimeter. Other conditions apply; confirm with your local planning authority.

How long does it take to get a farm building up?

The build itself is often the short part. Allow first for the prior approval determination: the local planning authority has 28 days to say whether approval is required. Then frame fabrication lead time, then groundworks and slab curing before erection. A full planning application instead of prior approval adds months. Start the consent route before you finalise the specification.

Is this quote service really free?

Yes, free to you and with no obligation to accept any quote. We pass your details only to agricultural building and grain store firms, who quote you directly. We may receive a fee from those providers, which is how the service is funded.